Addressing the East–West Capacity Bottleneck
Unveiled on November 16–17, 2026, the SALAM subsea cable initiative will extend roughly 5,500 kilometers across four segments and establish 10 new Cable Landing Stations, employing Alcatel Submarine Networks (ASN) wet-plant technology. The entire project receives backing from Malaysia's Universal Service Provision (USP) Fund. Existing submarine cables connecting Peninsular Malaysia to East Malaysia, including SKR1M which went live in 2017, are already running at approximately 85% capacity utilization. Implementation is set to commence in mid-December 2026, with phased rollout expected to conclude by Q1 2030.
Two-Phase Regulatory Framework and Governance Structure
The SALAM project was first introduced under Malaysia's National Budget 2026 in October 2025 and progressed through a structured two-phase regulatory procurement process managed by the Malaysian Communications and Multimedia Commission (MCMC) under the Communications and Multimedia (Universal Service Provision) Regulations 2002.
Departure from Earlier Consortium Model
Malaysia's earlier Sistem Kabel Rakyat 1Malaysia (SKR1M), which commenced operations in 2017, operated as a public-private consortium with joint ownership between TM and TIME dotCom. The SALAM procurement, by contrast, centers on a single designated universal service provider—TM Technology Services—combined with defined sovereign capacity reservations.
Technical Design and Landing Station Network
Under the MCMC award, TM Technology Services will oversee comprehensive planning, engineering, wet-plant procurement, marine installation, system integration, and operational management across four subsea segments utilizing Alcatel Submarine Networks technology.
Eastern Seaboard Hubs
- Cherating (Pahang)
- Sedili (Johor)
Western & Central Borneo
- Kuching
- Sibu (Matu)
- Bintulu (Samalaju)
Northern & Eastern Borneo
- Kota Kinabalu & Kudat
- Pulau Banggi
- Sandakan & Tawau
Sovereign Capacity and National Security Provisions
The MCMC mandate requires that four fiber pairs on the SALAM system remain permanently reserved for Malaysia's strategic national needs, including sovereign cloud infrastructure, government digital networks, and national cybersecurity resilience. This reservation also strengthens connectivity to remote island communities such as Pulau Banggi.
Financial Valuation and Equity Upside Potential
Following TM's disclosure to Bursa Malaysia, equity analysts at Kenanga Research released a valuation assessment on November 18, 2026, projecting that SALAM could deliver RM523 million (~US$127 million) in incremental commercial value—equivalent to approximately 13.6 sen (~US$0.033) per TM share—and generate up to RM150 million (~US$36.4 million) in annual commercial revenue by 2034 (based on an exchange rate of ~RM4.12 per US$1 as of November 2026).
Valuation Contingencies
Kenanga Research's RM523 million valuation assumes TM retains complete ownership of the SALAM wet plant and possesses unrestricted commercial rights to monetize capacity on non-reserved fiber pairs. However, TM and MCMC have not yet made public the final asset-ownership transfer terms, total fiber-pair count, or wholesale pricing framework under the USP agreement. As a result, analysts have excluded the RM523 million upside from base-case target prices, maintaining an Outperform rating at RM9.11 per share (~US$2.21) pending formal contract disclosure.
Construction Funding and Equity Value Mechanics
Understanding how a RM2.70 billion infrastructure investment translates into RM523 million of incremental equity value requires distinguishing between the source of upfront construction funding and the capture of post-2030 wholesale revenue streams.
Earnings-Neutral Build Through USP Fund Financing
The RM2.70 billion budget is entirely financed through Malaysia's Universal Service Provision Fund rather than TM's corporate balance sheet. Operating under a milestone cost-reimbursement structure, with RM2.43 billion allocated to wet-plant and landing station construction and RM270 million covering five years of fixed-fee operations and maintenance, TM incurs no upfront capex obligation, rendering the four-year build largely neutral to earnings.
Wholesale Operating Leverage Without Capital Burden
The RM523 million figure represents the discounted Net Present Value of post-2030 commercial wholesale revenues—projected to reach approximately RM150 million annually by 2034—generated from spare fiber pairs beyond the four government-reserved pairs. Because the RM2.43 billion upfront asset cost is subsidized by the USP Fund, TM avoids substantial depreciation charges against these future wholesale revenue streams.
Investor Takeaway: Conditional Option Value
The RM2.70 billion represents a government-funded pass-through construction budget, whereas the RM523 million (13.6 sen or ~US$0.033 per share) reflects the present value of capex-free wholesale bandwidth cash flows commencing in 2030. Realizing this upside depends on final MCMC–TM contract terms confirming TM's asset ownership, total commercial fiber-pair count, and unrestricted wholesale monetization rights.